Main Works
- Completion of project fence
- Construction of site offices
- Demolition of existing builds
- Site clearance and marking out
- Completion of new 6m wide gov't road to project
- Setup of 2 container site offices with AC, water and electric
- Install marketing billboard vinyl panels and steel frame
- Construction tender process
- Piles driven into ground in preparation for caps
- Conducted ground breaking blessing
- Ceremonial first concrete pouring
- Completion of piling the entire site
- Completion of building A Concrete Structure 100%
- Completion of building A Roof Structure Steel
- Commencement of roof finishes, tiles, fascia and eaves
- Completion of internal double skin walls with sound insulation
- Continue work to external and internal Q-con block walls
- Commencment of sanitary pipe work first fix
- Commence installation of electrical conduits and wall boxes
- Continue work forming and concreting window and door openings
- Start plastering walls to the Mock-Up Unit
- Show unit floor & ceiling complete
- Show unit kitchen & furniture, doors and windows installed
- Show unit final paint complete
- Building D:
• Foundations Complete • Ground Slap Finished
• Formwork and Steel Reinforcement Prep to 1st floor
• Concrete Placing to 1st floor
• Columns+Roof Beams Complete
• Roof Structure Complete
• Commence Roof Tiling
- Start Execavation of Building C Footings
- Building C Footings and Stub Columns Complete
- Building D:
• External Block Walls
• Cavity Wall Insulation
• Internal Walls & Door Openings
• Block Above Lintels
- Building C:
• Ground Slab Prep
• Ground Floor Concrete Pour
• View from Rear Boundary
• Ground Slab Steel Prep
• Ground Slab Concrete Pour
• First Floor Beam Framing
• First Floor Steel and Formwork
- Building A:
• Electrical Wiring and Start
Ceilings
- Building C:
• Start Block Walls (Cavity Work)
• Complted Roof
• Interior/Exterior Block Work
• Ready to Start Rendering
- Building D:
• Interior Render Walls Complete
• Wall Rendering Complete
- Building E:
• Basement and Watertank
Footing & Wall Reinforcement
• Waterproof Retaining Walls
Prior to Back Fill
- Building A:
• Plaster ceilings and insulation
complete
• Aluminium door and window
completeinstallation 80% done
• Rain gutter and downpipes
installed
- Building B:
• Break ground last week of April
- Building C:
• Internal and external wall
rendering complete
• First fix electrical and
sanitary complete
- Building D:
• Electrical conduits/cable,
sanitary and air conditioning
pipe work installed in ceilings
• Start metal framework
for gyprock ceilings
• External Conwood ceilings
commenced
- Building E:
• Swimming pool concrete structure
and pool deck complete
• Reception, bar, restaurant and
commercial kitchen slab complete
• Commenced work to level 1
fitness centre
|